On-Grid Solar and Kerala State Electricity Board (KSEB )
30-04-21- Feasibility application submitted to KSEB Kozhencherry section 07-07-21- Feasibility report generated by system 28-07-21- Feasibility report received in hand 19/07/21- Advance Payment to Solar installer (Pravasi Est) 20/07/21- Fabrication work started 26/07/21- Installation completed 28/07/21- Application for Solar testing to KSEB submitted -- Followed-up with KSEB Kozhencherry section AEE several times during this period. AEE said that the sub engineer (Mr. Unnikrishnan was on 2 months of leave due to medical reasons) 04/10/21- Contacted CGRF & Pathanamthitta division office 8/10/21- Request for Meter testing forwarded to TVA meter testing division 22/10/21- Inspection Officer (Mr. Pradeep) from Meter testing division inspected premise and commented that the manual isolator is missing and sped away 29/10/21 - Request for re-inspection after rectifying issue (installed manual isolator) submitted to Kozhencherry Sectio...